Utility Projects:
TNC Projects 1
TNC Projects 2
TNC Projects 6
TNC Projects 1
1/6
TNC Projects 1
TNC Projects 2
TNC Projects 5
TNC Projects 1
1/5
Power Distribution Projects:
Owner: TREC
Location: Variable
Service: High Voltage Substation
Complies with International Codes and detail of several types of MITSUBISHI, ABB, SIEMENS, HYUNDAI etc installation and equipment, successfully constructed over 24 High Voltage Substation Projects (including GIS and Mobile substations) within ISO-9001, ISO-14001 and OHSAS-18001 framework.

Power Transmission Lines:
Owner: TREC
Location: Rey
Service: Transmission Line
Project was constructing of a 207 Km Double Circuit 230 KV National Power Network

Surkhon Refinery Gas Pipe Line Project:
Owner: NIGC
Location: Surkhoun
Market/Service: LNG Pipeline
The project involved the construction of 103 Km 56-inch National Gas Pipeline Network with capacity of 14.4 million cubic meter of LNG per day